Spray polyurea elastomers for pipeline
antisepsis
1. Plan
A. Material
polyurea: ILSAN Polyurethane (Shanghai) Co., Ltd., without
impregnant
primer: ILSAN Polyurethane (Shanghai) Co., Ltd. one component,
solidify in humidity
protective coating: ILSAN Polyurethane (Shanghai) Co., Ltd.
with impregnant
B. design for coat
pipeline surface + primer + polyurea + (protective coating)
If there is higher requirements on the appearance of outside
elastomer, another layer of protective coating should be added
on it. If the elastomer is underfloor or not directly exposed
outdoors, the protective coating is not needed.
2. pretreatment of steel tube surface
Before construction, completely clear the dust, oil stain
and other foreign matters on the base level of pipeline. Then
warm up the steel tube at a temperature of 40℃-60℃, then do
pretreatment. The above sequence can not be changed, especially
spraying sand. The pressure can compress the chipping into
the clearance in the surface on steel tube. It is quite complex
to clear the chippings, and may affect the adhesive strength
of polyurea.
Pretreat the steel tube surface by spraying sand or shot blasting,
and the quality should up to Sa21/2 class of GB/T 8923 in
"the Class of rust and descaling of steel surface before
application", the
depth of should reach 50μm-75μm.
Level the surface with grinding wheel.
After pretreatment, clear the surface of steel tube and prevent
humidity, rustiness and secondary pollution. Clean the surface
with impregnant, when it completely volatilizes, coat the
primer or spray elastomers within 4h, after 4h or it rusts
again, please pretreat another time.
If the condition allows,take away the impregnant with high
pressure dry air.
3. spray polyurea
1) calculation of raw material dosage
2) equipment condition:
core: America GUSMER Company H-20/35 series, HV-20/35 series,FF-3500,FF-2500
etc.
ejection gun: GX-7 DI,GX-7 400,GX-8
mixing space: 453#
regulate the pressure and temperature that the provider recommended
3)Finished the preparation of raw materials and equipments
and the installation, spray polyurea according to the technological
process that the provider recommended.
Please contact ILSAN Polyurethane (Shanghai) Co., Ltd. to
learn more detail technological process.
4. construction of protective coating
coat protective coating on the surface of polyurea elastomers
in order to prevent yellow stain
5. quality guarantee
Perdon in charge of the project should carry out a progress
report to guarantee that the project is in accordance with
the requirements of provider.
The manufacturers promised that they will provide services
of on-the-spot examination, technique support and guide for
material usage, etc. if is necessary before the construction
finished.
When the construction finished, examine the finished products
and solve the problems left over. Manufacturers can ask the
third party to finish the service. Then, tidy the scene.
After the beginning, spray small pieces of elastomers sample
periodically, examine their capabilities, make a record and
keep them until the finish of construction.
|
|