Polyurethane
and polyurea spray elastomers waterproof construction method
In
order to guarantee the quality of contruction, the following
process can be a reference:
1. clear levelling blanket
Before
construction, completely clear the levelling blanket in order
to take away the cement dust, oil stain and other foreign
matters. Use steel brush and hammer or spray sand to clear
away the cement foam, parting agent and firming agent. Use
grinding wheel to level the surface. Complement the crack
with filler. Use 107 gluewater and mud mixture which contains
20% cement or vinyl acetate and cement mixture to level the
concave. The height difference should be not over 2mm. Clear
away the dust with high pressure blower, swab or cotton yarn,
it affects the quality of spray polyurea elastomers a lot.
2. treatment for special parts
Please ask ILSAN Polyurethane (Shanghai) Co., Ltd. about the
treratment for special parts, such as large crack(above 5mm),
rimula (below 5mm) pipeline surrounding, drainpipe surrounding,
roofing interlayer waterproof and extrude parts.
3. examine the water ratio of levelling blanket
elastomers should be sprayed on dry levelling blanket, therefore,
do not construct until the water ratio of cement ground below
8%.
4. spread coating primer
One component filtering primer rigidifying at normal tempreture
is choosed for the concrete base level and coated with hair
brush, round brush or in the way of spray.
The function of primer is to cut off the humidity of base
level infiltrate upowards, prevent bulge and desquamation
of spray elastomers, further reinforce the base level, improve
the cohesional strength between spray elastomers and base
level, and prevent appearing pinprick or air vent.
5. Spray elastomer
5.1. calculation
of elastomer raw material dosage
confirm the dosage and cost of raw material according to the
thickness and calculation method that the provider recommended.
5.2. equipment condition
mainframe: America GUSMER Company, H-20/35 series, HV20/35
series,FF-3500,FF-2500 etc.
ejection gun: GX-7 DI,GX-7 400
regulate the pressure and temperature that the provider recommended
5.3. construction condition
try to keep away from humidity, especially in winter, the
best construction time is between 10 am. and 4 pm.
5.4. last treatment
Finished spraying elastomers, examine carefully if there is
necessary for complement. Meanwhile, spray the edge and special
parts.
6. examine construction quality
Construct the protective layer only when the quality inspection
organization says the quality of elastomers is up to standard.
7. construct protective layer
Coat protective coating, or do surface treatment with carborundum,
or make a rigid protective layer on the elastomers.
8. Points for attention
Smoking, open flame, high temoerature, jointing or electric
spark are forbidden when constructing. (especially the windy
day)
Note the splash of material when constructing on the roof,
overhead and bridge(automobile, window, etc.).
Workers must wear safety helmet and follow the safety rules.
9.Sketch
map of construction

|
|